GHAZIABAD DEVELOPMENT AUTHORITY Vs URMILA
Case number: C.A. No.-003727-003727 / 2001
Diary number: 17914 / 2000
Advocates: T. MAHIPAL Vs
KRISHAN SINGH CHAUHAN
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.3727 OF 2001
Ghaziabad Development Authority ...Appellant(s)
Versus
Urmila ...Respondent(s)
With Civil Appeal No.6955 of 2004
O R D E R
Civil Appeal No.3727 of 2004:
Heard learned counsel for the parties.
The District Consumer Disputes Redressal Forum, Ghaziabad (for short,
“the District Forum”) by its order dated 20th January, 1999, partly allowed the
complaint filed by respondent-Urmila and directed Ghaziabad Development
Authority (hereinafter referred to as “the Authority”) to remove the defects in the
house allotted to the respondent with the stipulation that if the needful is not done,
then decision will be taken in the execution proceedings for award of the amount
spent by the complainant on removal of the defects. The District Forum further
directed the Authority to pay interest to the respondent at the rate of 15 per cent per
annum for the period from 1st April, 1995 to 6th September, 1996 on the amount
deposited by her up to 31st March, 1995 and Rupees four thousand towards mental
agony and cost of litigation as, in its opinion, there was delay on the part of the
Authority in delivering possession of the house to the respondent. The said order was
confirmed in appeal by
...2/-
- 2 -
the State Consumer Disputes Redressal Commission, U.P.(for short, “the State
Commission”) and when the matter was taken in revision before the National
Consumer Disputes Redressal Commission (for short, “the National Commission”),
the same has been dismissed. Hence, this appeal by special leave.
Learned counsel appearing on behalf of the appellant-Authority submitted
that the District Forum was not justified in directing it to remove the defects in the
house allotted to the respondent on the basis of report dated 15th September, 1996
prepared by the Engineer appointed by her because she had taken possession of the
house without making any grievance regarding the so-called defects. In our view,
there is no merit in the submission of the learned counsel and the direction given by
the District Forum does not call for interference because the Authority did not adduce
any evidence before the District Forum to controvert the report produced by the
respondent. If the house was free from defects on the date of delivery of possession
and the Authority thought that report dated 15th September, 1996 does not reflect the
true status of the house, then it could have, on receipt of the notice of the complaint,
deputed its own engineer for inspection and submitted report before the District
Forum to convince it that the grievance made by the respondent was untenable.
However, the fact of the matter is that no such report was produced by the Authority.
Therefore, we do not find any justification to interfere with the direction given by the
District Forum, which was confirmed by the State Commission as well as the National
Commission.
Learned counsel for the appellant next submitted that the District Forum
was not justified in awarding interest on the amount deposited by the respondent up
to 31st March, 1995 because there was no delay in the delivery of possession of the
house. Learned counsel pointed out that in terms of letter dated 3rd February, 1993
the respondent was required to
...3/-
- 3 -
pay balance of the estimated cost by 30th July, 1995 but she did not pay the
instalments on due dates and the last one was paid after more than one year and four
months of the delivery of possession. Learned counsel for the respondent fairly
admitted that his client did not pay instalments of the balance estimated cost on due
dates. In this view of the matter, the Authority cannot be blamed for delay in
handing over possession of the house to the respondent. Even otherwise, we are
satisfied that the finding recorded by the District Forum on the issue of delay in the
delivery of possession is based on total misreading of letter dated 3rd February, 1993
and the pleadings of the parties. The District Forum completely ignored the fact that
the respondent had not paid even a single instalment on due date and even as on the
date of handing over possession, substantial amount was due from her. A reading of
letter dated 3rd February, 1993 shows that the respondent was required to pay
instalments of the balance estimated costs between 30th January, 1993 and 30th July,
1995. It was mentioned in that letter that the expected date of delivery of possession of
the house would be during the year 1995, which would necessarily mean after
payment of the instalments by 30th July, 1995. It was further mentioned in the letter
that if the house is made ready before one or more instalments are due, then
possession of the same would be made over to the complainant only upon payment of
entire balance instalments in one lump sum. In paragraph (4) of the complaint the
respondent has given a table of the instalments paid by her. A reading thereof makes
it clear that not a single instalment was paid within time. Till the year 1994, the
respondent paid only a sum of Rupees one lakh. No payment was made in the year
1995 and substantial amount was paid between the years 1996 and 1998. The last
instalment was paid on 16th January, 1998. From these facts it is evident that there
were laches on the part of the respondent
...4/-
- 4 -
in payment of the instalments. In this view of the matter, it must be held that District
Forum was not justified in awarding interest upon the amount deposited till 31st
March, 1995 and the sum of Rupees four thousand by way of compensation for
mental agony as also cost of litigation.
Accordingly, the appeal is allowed in part and the impugned order passed
by the District Forum awarding interest from 1st April, 1995 till 6th September, 1996
and sum of Rupees four thousand by way of compensation and the orders of the State
Commission and the National Commission confirming the same are set aside.
CIVIL APPEAL NO. 6955 OF 2004:
Heard learned counsel for the parties.
By the impugned order, the National Consumer Disputes Redressal
Commission (for short “the National Commission”), has remanded the matter to the
District Consumer Disputes Redressal Forum, Ghaziabad (for short, “the District
Forum”) for calculation of the amount payable to the respondent as also the amount
due to the appellant-Authority. The District Forum, on remand, is directed to pass a
fresh order, as directed by the National Commission, after taking into consideration
the order passed by us today in Civil Appeal No. 3727 of 2001.
With this direction, the civil appeal is disposed of.
......................J. [B.N. AGRAWAL]
......................J. [G.S. SINGHVI]
New Delhi, January 22, 2009.