15 April 2009
Supreme Court
Download

G. RAMACHANDRA REDDY & CO. Vs UNION OF INDIA

Case number: C.A. No.-002479-002479 / 2009
Diary number: 2454 / 2005
Advocates: S. R. SETIA Vs ANIL KATIYAR


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 23  

                                                            REPORTABLE

                IN THE SUPREME COURT OF INDIA

                CIVIL APPELLATE JURISDICTION

                CIVIL APPEAL NO.         2479 OF 2009                  (Arising out of SLP (C) No.3182 of 2005)

G. Ramachandra Reddy & Co.                                ... Appellants

                                  Versus

Union of India & Anr.                                     ... Respondents

                                  WITH

                 CIVIL APPEAL NO. 2536 OF 2009                  (Arising out of SLP (C) No.9624 of 2006)

                            JUDGMENT

S.B. Sinha, J.

1.    Leave granted.

2.    Jurisdiction of a court to interfere with an arbitral award involving

interpretation of a contract is involved in these appeals which arise out of a

judgment and order dated 4.10.2004 passed by a Division Bench of the High

Court of judicature at Madras allowing an appeal from a judgment and order

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 23  

                                    2 dated 14.1.2000 passed by a learned Single of the said court making the

award made by Respondent No.2 herein a rule of Court.

3.     For the work of construction of "Married accommodation for

MCPOs/CPOs/POs and Junior Sailors at Naval Air Station, Arakkonam" by

the Union of India, an advertisement was issued; pursuant whereto appellant

submitted its tender on or about 9/17.7.1988 marked as Exhibit C-2. In its

forwarding letter, it was stated :

             "We have kept ready all the men and material for               early commencement of the work. The technical               personnel engaged by the firm have the vast               experience in the execution of major building               projects. The total labour component involved in               this work is forty per cent of the scope of the               contract. We can deploy the huge skilled and               unskilled labour force already on our rolls for all               the works along with the machinery for successful               completion of the work positively as per targeted               time schedules of the Department. The latest               ITCC and partnership deed are enclosed as               required."

      A post script added thereto reads as under :

             "When our tender opened and Rates Read out,               Please Read out over (+) 2.25% under item 1 of               the schedule quoted percentage and total value               considered accordingly."

4.     Respondent, by a letter dated 19.7.1988 (marked as Exhibit C-3)

replied thereto, stating :

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 23  

                              3       "On scrutiny of your forwarding letter the       following comments are made :-       (a)    The Labour component in the work is 20 as              included under Special Condition No.17 on              Serial Page 94 of the tender and not 40 as              referred to by you.       (b)    In case of acceptance of your tender              mobilization advance of Rs.35.00 lakhs will              be paid against BGBs as per conditions of              the tender.       (c)    It is seen that the way the revision has been              made in the quoted percentage for Schedule              ‘A’ Part I does not go well with the status of              your firm. However, your tender is being              considered with the reduction of minimum              2.25% over quoted percentage for Schedule              ‘A’ Part I as also read out at the time of              opening      of    tenders   wherein     your              representative was also present."

Yet again on 5.8.1988, appellant in reply thereto, inter alia, stated :

     "1. We hereby clarify that our rates are worked       out and quoted taking total labour component       involved in the scope of work as 40%. As such the       department may please evaluate our tenders on the       same basis and consider accordingly.

           XXX                XXX                 XXX

     After ascertaining this just before dropping the       tender in the tender box, our Managing Partner had       to include an extra at 2.25% towards Turnover       Sales Tax liability and the vertical line in the sign       (+) has been hurriedly put as shown here once       again (+).

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 23  

                                   4              Thus, our quoted rates for item 1 of the schedule is              18.5% i.e. 16.25% quoted by us in the schedule              and plus 2.25% quotd in the covering letter along              with our tender against item 1 of the schedule. We              regret for the misunderstanding led in this regard."

     Offer of the appellant was accepted by the respondents in terms of its

letter dated 11.8.1988, the relevant portion whereof reads as under :

            "Reference your letter No.Nil dated 9/17.7.1988              forwarding the tender for the above mentioned              work.              2.    On behalf of the President of India, I hereby              accept your tender for the work mentioned above              for the Lump Sum of Rs.7,54,03,216.00 (Rupees              Seven Crores Fifty four lakhs three thousand two              hundred and sixteen only).              3.    This contract is allotted the number "CA              No.CEMZ/ARK/4 of 1988-89" which will be              quoted by you in all future correspondence in              connection with this contract.              4.     The tender enquiry, your tender, the letter              referred to above and this letter shall be the sole              repository of the contract."

     With the said letter, the details of amended Lump-sum was appended

which reads as under :

               "DETAILES OF AMENDED LUMP SUM

             i) Lump sum amount originally          Rs. 7,67,22,728.00                  quoted

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 23  

                                        5

             ii) Deducted for reduction of (-)         Rs.   13,91,512.00               2.25% offered on Schedule ‘A’ Part               I vide your letter No. NIL dated               9/17 July, 88 while forwarding the               tender (i.e. 2.25% on               Rs.6,18,45,000/-)

             Note : Consequent on SI (ii) above               the Representing percentage on               Schedule ‘A’ Part I stands amended               to "+ 14%"

             Amended Lump Sum                          Rs.7,54,03,216.00

            (Rupees Seven crores fifty four lakhs three thousand two              hundred and sixteen only)"

6.    Indisputably, whereas the main letter dated 11.8.1988 was signed by

one L.D. Sharma, Brig. Chief Engineer as accepting officer for and on

behalf of the President of India, the appendix was signed by some other

person for ‘Accepting Officer’.          Indisputably, the representative of the

appellant also signed the said letter.

     The said contract, however was terminated on or about 10.7.1991

7.    Disputes and differences having arisen between the parties, the

arbitration agreement which formed part of the general condition of the

contract as also special condition of contract was resorted to. Respondent

No.2 was appointed as the Arbitrator.

     Before the learned Arbitrator, appellant put forth eight claims, being :

6

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 23  

                                  6             "(a)   Dispute regarding additional payment of                    2.25% over the quoted rates under item 1 of                    Schedule A with an overall effect of 4.5%                    over what has been paid to the plaintiff.             (b)    Dispute regarding percentage of labour                    component in the work with reference to the                    escalation in labour rates and for                    consequential in labour rates and for                    consequential payments to the plaintiff.             (c)    Dispute regarding escalation with reference                    to the extra payment of labour involved in                    construction of high rise building.             (d)    Dispute regarding legality of the termination                    of the plaintiff’s contract and for                    consequential damages.             (e)    Dispute regarding release of the plaintiff’s                    plant and equipment, together with damages                    for the use of the equipment by the                    defendant and in default payment of the                    market value of the plant and equipment as                    on the date of termination, together with the                    damages as aforesaid.             (f)    Dispute regarding balance payment for the                    work done and material supplied by the                    plaintiff.             (g)    Interest at 24% p.a. on all amounts due to                    plaintiff and awarded by the arbitrator from                    the date when the cause of action for the                    claim arose, till the date of payment to the                    plaintiff."

8.    Respondent repudiated the said claims of the appellant. Respondent

No.2 made and published an award on 17.9.1996. While claims Nos.1 and 5

were allowed in part, claims No.2 and 4 were allowed in toto. Claim No.3

7

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 23  

                                   7 was allowed for the amount to which the appellant itself had restricted its

claim to.

     Counter claim of the first respondent was rejected.

9.    First respondent filed an application under Section 30 of the

Arbitration Act, 1940 (hereinafter called and referred to for the sake of

brevity as ‘the Act’).

     A learned Single Judge of the High Court rejected the said objection,

opining that the award did not warrant any interference. The learned Single

Judge noticed that claim Nos. 5 and 6 had not been disputed by the first

respondent and counter claim No.4 was not pressed. It was, therefore,

directed payment of a sum of Rs.2,78,17,530.01 p. with further interest @

6% per annum from the date of decree till the date of realization. The

counter claim was also dismissed.

10.   First respondent preferred an intra court appeal thereagainst in terms

of clause 15 of the Letters Patent of the High Court read with Section 39 of

the Act. The Division Bench of the High Court allowed the said appeal in

part in respect of three items of claim. The objection in relation to fourth

item was also dismissed.

11.   Both parties are here before us aggrieved by and dissatisfied with the

said judgment.

8

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 23  

                                     8 12.     The three heads of claim which were allowed by the respondent No.2

in favour of the appellant are as under :

(i)     Claim of 2.25% over and above the base price as specified in Item

       No.1 of Schedule A;

(ii)    claim of escalation towards labour component whether 40% or 21%;

       and

(iii)   claim towards higher minimum wages paid to the workmen in terms

       of a Government of India notification dated 14.10.1986.

       The fourth claim which was allowed related to loss of profit allegedly

suffered by the petitioner for illegal termination of the contract.

13.     Mr. Gurukrishna Kumar, learned counsel appearing on behalf of the

appellant, would submit :

(1)     That the Division Bench of the High Court committed a serious error

       in so far as it failed to take into consideration the distinction between

       an excess of jurisdiction and an error apparent on the face of the

       award and as the respondent’s objection was not in relation to the

       exercise of excess jurisdiction by the arbitrator, a strict scrutiny test

       should have been applied.

9

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 23  

                                   9 (2)   The Division Bench of the High Court committed a serious error of

     law in so far as it failed to take into consideration that an error

     apparent on the face of the award would not entitle it to enter into the

     merit of the matter as the same is confined to the award itself or any

     note appended thereto.

(3)   Interpretation of an agreement admittedly being within the realm of

     the jurisdiction of the Arbitrator, interference therewith is not

     permissible even if the court takes a different view.

14.   Mr. B.B. Singh, learned counsel appearing on behalf of the

respondent, on the other hand, would urge :

1)    As the jurisdiction of the Arbitrator emanates from the contract, he

     must exercise the same within the four corners thereof.

2)    Interpretation of a contract although fell within the jurisdiction of the

     Arbitrator but in construing the same, he could not have ignored any

     material document, namely, the final contract entered into by and

     between the parties on 11.8.1988 and based his interpretation only on

     the basis of letter of the contractor dated 9/17.7.1988 and, thus, he

     must be held to have misconducted himself and the proceedings.

10

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 23  

                                   10 15.   Before adverting to the rival contentions, as noticed hereinbefore, we

may briefly notice the reasonings adopted by respondent No.2 in making the

award.

The learned Arbitrator proceeded on the basis that :

(1)   The letter of the contractor dated 9/17.7.1988 formed part of the

     contract.

(2)   The intent of the parties must be ascertained from four documents

     which formed part of the contract and not de hors the same.

(3)   Appendix to the letter dated 11.8.1988 having been signed by a person

     other than the Accepting Officer who was authorized therefor, the

     same was not binding on the appellant.

(4)   Although the appellant had signed the work order, the same by itself

     would not lead to the conclusion that it was estopped and precluded

     from questioning the quantum of amount mentioned in the said letter

     dated 11.8.1988.

16.   In respect of claim No.1, the learned Arbitrator held :

           "On a consideration of the letters and the Exhibits             mentioned above, we have to state that a             concluded contract has taken place taking into             consideration the sign (+) mentioned in the             covering letter. Even assuming that there was a

11

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 23  

                                    11              mistake on the part of the respondent reading the              covering letter, the contract would remain              unaffected.              The contention of the respondent that when once              the claimant has accepted for the reduction, as is              found in Ex.R.7, which is the contractor’s work              order sheet, and which is signed by the contractor              on 14.9.1988., it has to be concluded that there is              an acceptance for the reduction. This argument of              the learned Counsel for the respondent is not well              founded. An acceptance of the contract will have              to be considered under the terms of Ex.C.5 dated              11.8.88. In the instance case it is common ground              that there is a concluded contract between the              parties and what remains is the interpretation of the              contract, Ex.C.5 it is not the case of the respondent              that Ex.C.5 is a counter offer which was accepted              by the claimant. On the other hand, it is agreed by              the respondent that acceptance of the contract is              solely based on Ex.C.5. The documents filed              before me in this case clearly establish the sigh (+)              which is more particularly referred to in Ex.C.5 as              the sole repository of the contract. (underlining is              mine) In such a case, it has to be concluded that              Ex.R.1 is the clear acceptance of the contract. It              has to be further noted chat as per the terms of              Section 7(2) of the Contract Act, if the proposer              does not insist that his proposal should be accepted              in the prescribed manner, he in fact accept the              acceptance."

     In respect of claim No.2, the relevant condition of contract, namely,

clause (17) although specified that for the purpose of escalation of the labour

component, the value of contract should be taken as 21% but as the appellant

claimed 40% in its offer, the same would prevail over the contract, stating :

12

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 23  

                                  12            "I state that special condition to the contract that is            clause 17 at Page 4 specifies that for the purpose of            escalation the labour component for the value of            work will be taken as 20% which was later            changed as 21%. Similarly, fuel component which            was shown as 1.5% in the agreement was changed            as 2% and the material component which was            shown in the agreement on page 90 as 60% was            changed into 58%. In other words, the total            component towards labour, material and fuel            comes to 81%. The claimant has not claimed            anything in excess of 81%, for, the escalation            clause in the agreement provides, the escalation for            an amount not exceeding 81% of the value of the            work done. All that he has claimed is, towards            fuel 2%, towards material 39% and towards labour            40%. This change in labour component at 40% is            based on Ex.C.22 (R1) dated 9/17.07.88 which has            become part of the tender bid. This part of the            offer that is tender bid, has been accepted by the            respondent, that is to say, that this 21% mentioned            in the contract has been substituted as 40%. The            claimant has made this fact clear in all his            subsequent letters. In other words, the contention            of the claimant is that the covering letter Ex.C.2            (R1) is part of the tender bid, and since the tender            bid has been accepted without any modification,            the figure 21% in the condition, has, therefore, to            be substituted by 40%. It is on this basis the            claimant claims that the labour component should            be paid at the rate of 40%, while material            component would consequently come at 39% and            the fuel component will remain at 2%."

    In respect of claim No.3, it was held that in view of the notification

issued by the Central Government dated 14.10.1980, the minimum wages

payable to the workmen being over and above 20% the general wages, the

13

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 23  

                                   13 same would be payable to all the workmen and not those employed in high

rise portions of the building.

17.   The Division Bench, however, set aside in part the award in respect of

the aforementioned claims stating as under :

            "However, we find some substance with regard to              the claim No.4, loss of profit, there was an              admitted delay in handling over the site and supply              of materials. We confirm both the award of the              Arbitrator and the order of the learned Single              Judge with regard to Claim No.4, loss of profit."

18.   We may, at the outset, notice the legal principles governing the

dispute between the parties. Interpretation of a contract may fall within the

realm of the Arbitrator. The Court while dealing with an award would not

reappreciate the evidence. An award containing reasons also may not be

interfered with unless they are found to be perverse or based on a wrong

Proposition of law. If two views are possible, it is trite, the Court will

refrain itself from interfering. {See State of U.P. v. Allied Constructions

[(2003) 7 SCC 396]}.

     In Pure Helium India (P) Ltd. v. Oil & Natural Gas Commission

[(2003) 8 SCC 593], this court, upon referring to the decisions in Allied

Constructions (supra), K.R. Raveendranathan v. State of Kerala [(1998) 9

SCC 410], H.P. Seb v. R.J. Shah & Co. [(1999) 4 SCC 214], Rajasthan State

14

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 23  

                                   14 Mines & Minerals Ltd. v. Eastern Engg. Enterprises [(1999) 9 SCC 283],

Food Corporation of India v. Surendra, Devendra & Mahendra Transport

Co. [(2003) 4 SCC 80] and Shyama Charan Agarwala & Sons v. Union of

India [(2002) 6 SCC 201], opined as under :

           "41. The principles of law laid down in the             aforementioned decisions leave no manner of             doubt that the jurisdiction of the court in             interfering with a non-speaking award is limited.             42. The upshot of the above decisions is that if the             claim of the claimant is not arbitrable having             regard to the bar/prohibition created under the             contract, the court can set aside the award but             unless such a prohibition/bar is found out, the             court cannot exercise its jurisdiction under Section             30 of the Act. The High Court, therefore,             misdirected itself in law in posing a wrong             question. It is true that where such prohibition             exists, the court will not hesitate to set aside the             award."

     In Sudarshan Trading Company v. Government of Kerala & Anr.

[(1989) 2 SCC 38], the law was laid down in the following terms :

           "28. It was submitted before us that the High Court             had exceeded its jurisdiction in acting in the             manner it did on these aforesaid aspects. The first             question, therefore, that arises for consideration in             this case is, whether the award in question was a             speaking award or not. In our opinion, the award             was not a speaking award. An award can also be             set aside if the arbitrator had misconducted himself             or the proceedings or had proceeded beyond his             jurisdiction. These are separate and distinct             grounds for challenging an award. Where there are

15

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 23  

                                       15                 errors apparent on the face of the award it can only                 be set aside if in the award there is any proposition                 of law which is apparent on the face of the award,                 namely, in the award itself or any document                 incorporated in the award."

      It was furthermore observed :

               "29. The next question on this aspect which                 requires consideration is that only in a speaking                 award the court can look into the reasoning of the                 award. It is not open to the court to probe the                 mental process of the arbitrator and speculate,                 where no reasons are given by the arbitrator, as to                 what impelled the arbitrator to arrive at his                 conclusion."

19.    Jurisdiction of the Court to interfere with an award made by an

Arbitrator is limited. One of the grounds therefor is the error apparent on the

face of the award. We have noticed hereinbefore some precedents operating

in the field.

      What is an error apparent on the face of an award and legal

misconduct is stated in State of Rajasthan v. Pure Construction Co. Ltd. &

Ors. [(1994) 6 SCC 485], in the following terms :

               "As reference to arbitration of disputes in                 commercial and other transactions involving                 substantial amount has increased in recent times,                 the courts were impelled to have fresh look on the                 ambit of challenge to an award by the arbitrator so                 that the award does not get undesirable immunity.                 In recent times, error in law and fact in basing an

16

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 23  

                                   16             award has not been given the wide immunity as             enjoyed earlier, by expanding the import and             implication of "legal misconduct" of an arbitrator             so that award by the arbitrator does not perpetrate             gross miscarriage of justice and the same is not             reduced to mockery of a fair decision of the lis             between the parties to arbitration. Precisely for the             aforesaid reasons, the erroneous application of law             constituting the very basis of the award and             improper and incorrect findings of fact, which             without closer and intrinsic scrutiny, are             demonstrable on the face of the materials on             record, have been held, very rightly, as legal             misconduct rendering the award as invalid."

     It was furthermore stated :

           "Error apparent on the face of the record does not             mean that on closer scrutiny of the import of             documents and materials on record, the finding             made by the arbitrator may be held to be             erroneous. Judicial decisions over the decades             have indicated that an error of law or fact             committed by an arbitrator by itself does not             constitute misconduct warranting interference with             the award."

     In Trustees of the Port of Madras v. Engineering Constructions

Corporation Ltd. [(1995) 5 SCC 531], This Court opined :

           "14. ... A note of clarification may be appended,             viz., where the parties choose to refer a question of             law as a separate and distinct matter, then the             Court cannot interfere with the award even if the             award lays down a wrong proposition of law or             decides the question of law referred to it in an             erroneous fashion. Otherwise, the well-settled             position is that an arbitrator "cannot ignore the law

17

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 23  

                                    17              or misapply it in order to do what he thinks is just              and reasonable". [See Thawardas Pherumal v.              Union of India]

     It was clarified :

                   20. The proposition that emerges from the                     above decisions is this: in the case of a                     reasoned award, the court can interfere if the                     award is based upon a proposition of law                     which is unsound in law. The erroneous                     proposition of law must be established to                     have vitiated the decision. The error of law                     must appear from the award itself or from                     any document or note incorporated in it or                     appended to it. It is not permissible to travel                     beyond and consider material not                     incorporated in or appended to the award."

20.   We may, however, notice that in Food Corporation of India v.

Joginderpal Mohinderpal & Anr. [(1989) 2 SCC 347], referring to a large

number of decisions, a Division Bench of this Court held :

            "... It has to be borne in mind, however, that              wrong statement or conclusion of law, assuming              even that it was a wrong statement of law, was not              wrong statement of the proposition of law which              was the basis for decision in this award. Error of              law as such is not to be presumed; if there is legal              proposition which is the basis of the award and              which is erroneous as observed in Champsey              Bhara & Co., then only the award can be set              aside."

18

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 23  

                                     18 21.   Almost to the similar effect is the decision of another Division Bench

of this Court in Numaligarh Refinery Ltd. v. Daelim Industrial Company

Ltd. [JT 2007 (11) SC 73], wherein it is stated :

            "17. We have considered the rival submissions of              the parties. So far as the legal proposition as              enunciated by this Court in various decisions              mentioned above, it is correct that courts shall not              ordinarily substitute their interpretation for that of              the arbitrator. It is also true that if the parties with              their eyes wide open have consented to refer the              matter to the arbitration, then normally the finding              of the arbitrator should be accepted without demur.              There is no quarrel with this legal proposition. But              in a case where it is found that the arbitrator has              acted without jurisdiction and has put an              interpretation on the clause of the agreement which              is wholly contrary to law then in that case there is              no prohibition for the courts to set things right."

22.   A contract would warrant construction if the terms thereof are vague

and ambiguous. The letter exhibiting the offer of the appellant refers to four

different documents including the letter dated 9/17.07.1988 which was

marked as Exhibit C-2. Whether in the said letter, the appellant had asked

for increase of 2.5% over the base value or deducted 2.5% therefrom is a

matter of construction.

23.   The learned Arbitrator, it is not correct to contend, has not taken into

consideration the ultimate contract. He did take the same into consideration.

19

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 23  

                                    19 He, however, was of the opinion that the aforementioned four letters which

were said to be the sole repository of the contract formed part thereof.

     He, thus, took into consideration the relevant documents for arriving

at a finding as to whether they formed part of the contract. Offer of the

appellant was accepted.

24.   The first claim was in relation to disputes regarding additional

payment of 2.25% over the quoted rates under item 1 of Schedule A with an

overall effect of 4.5% over what had been paid to the plaintiff. The arbitrator

came to the conclusion that the letter dated 9/17.7.1988 (Ex.C.2) does not

make out whether the contractor intended to quote the price with +2.25%

and therefore, he held that a concluded contract has taken place after taking

into consideration the sign (+) mentioned in the above letter. The contract

will therefore still be enforced even if it is assumed that there was a mistake

on the part of the respondent. The High Court held that it was apparent on

the face of record that the contractor intended only to reduce 2.25%, which

was seen from Ex.C.5, which was final and concluded, claim no 1 fails for

that reason. But as the Arbitrator held that the letter of the contractor dated

9/17.7.1988 formed part of the contract, the claim cannot fail and therefore

the award of the Learned Arbitrator, in respect of claim No 1 must be

sustained.

20

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 23  

                                   20 25.   In relation to Claim No.2, the respondent relied on the fact that the

claimant received payment only at the rate of 21% towards labour escalation

in the several R.A.Rs and therefore, it has to be presumed that the claimant

is entitled to only 21%. The Arbitrator opined that the receipt of money at

21% cannot absolve the claimant from claiming at 40% as per the contract,

particularly, when it is clearly mentioned in Ex C.2 (R1) that 40% will be

the labour component which forms part of the contract, Ex C.5. The High

Court held that as the Department themselves gave 21% to the contractor,

and only 21% of escalation, which was in consonance with the special

conditions, which was apparent on the face of the record, the second claim

of escalation of 40% was to be set aside. But, keeping the same principle as

applied in relation to Claim No.1, the Arbitrator held that as the covering

letter (Ex.C.2) is part of the tender bid, and since the tender bid has been

accepted without any modification, the Figure of 21% has to be substituted

by 40%. Therefore, in respect of claim No.2, the impugned judgment of the

High Court cannot be upheld and the award of the Arbitrator is sustained.

26.   The matter might have been different had the respondents in

categorical terms rejected the offer made by the appellant as amended by its

letter dated 19.7.1988. It did not do it. Thus, the contract remained open for

construction.

21

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 23  

                                     21 27.   We have not been able to persuade ourselves to agree with the

reasonings of the Division Bench of the High Court. The award of the

learned Arbitrator in respect of claim No.1, therefore, must be sustained.

28.   Keeping in view the fact that the same principle would apply in

respect of claim No.2 also, the impugned judgment of the High Court cannot

be upheld.

29.   So far as Claim No.3 is concerned, the claim towards higher minimum

wages paid to the workmen is not in dispute. A high rise building is a high

rise building, it cannot be divided into two parts.

     What would constitute a high rise building was defined. A portion of

the building cannot be high rise and a portion would fall within the purview

of the said definition. The learned Arbitrator, in our opinion, had rightly

opined that the same workers may have to work for constructions of the

entire building as it will be impossible for any contractor to employ any

workmen to work exclusively for the high rise building. Furthermore, the

same workmen may have to work in different parts of the same building at

different times. It would lead to an absurd situation if the workmen at one

point of time are not paid the 20% of the excess amount and then paid the

same and yet again denied the same benefit. Interpretation of the High

Court, therefore, that high rise building mean portion of the building, in our

22

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 23  

                                   22 opinion, keeping in view the beneficent nature of the provisions, cannot be

accepted.

30.   The award of the Arbitrator in respect of claim No.4 has been

accepted by the Division Bench. Mr. B.B. Singh has drawn our attention to

clause 11(c) of the general conditions of contract to contend that in terms

thereof, no damages were payable.

     The question as to whether damages were payable for illegal

termination of contract cannot be a subject matter of contract. The learned

Arbitrator has categorically held that not only the termination of contract

was illegal, the same was mala fide. Furthermore, the contention raised

before us by Mr. Singh has not been raised before the High Court.

31.   In any event, there is a delay of 411 days in filing the SLP of the

respondent, for which no sufficient explanation has been given.

32.   For the reasons aforementioned, the appeal filed by Union of India is

dismissed and that of the appellant is allowed.             In the facts and

circumstances of the case, however, there would be no order as to costs.

                                           .....................................J.                                             [S.B. Sinha]

                                            .....................................J.

23

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 23  

                23                       [Cyriac Joseph] New Delhi; April 15, 2009