07 November 2006
Supreme Court
Download

B.H.E.L. Vs ANIL .

Bench: ARIJIT PASAYAT,S. H. KAPADIA
Case number: C.A. No.-006348-006348 / 2005
Diary number: 23755 / 2004
Advocates: PARIJAT SINHA Vs S. R. SETIA


1

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5  

CASE NO.: Appeal (civil)  6348 of 2005

PETITIONER: Bharat Heavy Electricals Ltd

RESPONDENT: Anil and Ors

DATE OF JUDGMENT: 07/11/2006

BENCH: Arijit Pasayat & S. H. Kapadia

JUDGMENT:

J U D G M E N T

KAPADIA, J.

What was the subject of the dispute decided by the Labour Court vide  its Award dated 5.7.1996 in ADJ case No. 31/90 to 44/90 ? This is the  question which we are required to answer in this civil appeal.

The facts giving rise to the civil appeal are as follows:

Bharat Heavy Electricals Limited ("BHEL") is the company  registered under the Companies Act, 1956 having its registered office at  New Delhi. Respondents 1 to 14 herein moved the Conciliation Officer  under Section 2-A of the Uttar Pradesh Industrial Disputes Act, 1947 ("the  said 1947 Act") stating, that there was a principal employer; that K.P. Singh  was a contractor under whom they were working as contract labour; that the  services were unlawfully terminated w.e.f. 1.12.1988, and accordingly, the  contractor should be asked to take them back in service with full back wages  w.e.f. 1.12.1988.

On 19.7.1989  BHEL filed its reply before the Conciliation Officer  inter alia stating that, respondents 1 to 14 herein were engaged by the  contractor; that the contractor was engaged by BHEL; and, that there was no  employer-employee relationship between BHEL on one hand and the said  respondents on the other hand.

Ultimately, the matter was referred to the Labour Court by way of a  reference under Section 4-K of the said 1947 Act. Before the Labour Court  BHEL contended, that respondents 1 to 14 were malis (gardeners); that they  were engaged by the contractor; that these malis were required to clean  parks; that in the vast area of land owned by BHEL, they were required to  keep the campus neat ant clean; that they had worked for a brief period  1.6.1988 to 24.10.1988; and, that they were casual workmen, who were not  entitled to be given work on all the days and, therefore, there was no  industrial dispute between BHEL and the said respondents within the  meaning of Section 2-A of the said 1947 Act. By the written statement,  BHEL further contended, that respondents 1 to 14  were never paid wages  by BHEL; that they never worked under their supervision and control, and  that the rights, if any,  of the said respondents were only against their  contractor. BHEL further contended that the period of contract commenced  on 1.6.1988 and ended on 24.10.1988.

At this stage, we quote hereinbelow the terms of reference made to the  Labour Court:

"Whether termination of services of Anil son of  Shri Vikram Singh by his employers from 1.12.88  was justified and/ or lawful ? If not then the

2

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5  

benefit/ relief the worker concerned is entitled to  \005."

By award dated 5.7.1996 the Labour Court held, that respondents 1 to  14 herein had worked for more than 240 days as malis; that work was taken  from them by the contractors; and, that the services stood terminated from  1.12.1988 without complying with the provisions of Section 6-N of the said  1947 Act. In the said award, the Labour Court observed that, the workers  themselves have proceeded on the footing that they were engaged by the  contractors, but the work which they performed was for BHEL. The Labour  Court came to the conclusion that non-employment of workers w.e.f.  1.12.1988 constituted termination under Section 2-A of the said 1947 Act.  The Labour Court held that, BHEL had retained its control over the workers  and, therefore, respondents 1 to 14 cannot be said to be the workers only of  the contractor. Consequently, the Labour Court held that, BHEL was the  principal employer and the contractor was the immediate employer. It  further opined that, respondents 1 to 14 had worked for 240 days and that  their services were wrongly terminated in breach of Section 6-N of the said  1947 Act. In the circumstances, the Labour Court held that the termination  of services of respondents 1 to 14 by the contractor was not justified and  lawful and that BHEL also was liable for wrongful termination.  Accordingly, the Labour Court directed BHEL to re-employ respondents 1  to 14 in their services or get them employed under the contractor.

The said award was challenged by BHEL in the High Court by way of   writ petition. By judgment and order dated 17.2.1999, the High Court upheld  the award of the Labour Court saying that it did not suffer from any  illegality or irregularity. The High Court affirmed the finding of the Labour  Court that respondents 1 to 14 had worked under the control of BHEL and  that BHEL was the principal employer of these workmen.

Aggrieved by the decision, BHEL carried the matter by way of special  leave petition to this Court. By judgment dated 21.7.2003 the Division  Bench of this Court held, that the services of these workmen were  wrongfully terminated, that they had worked for more than 240 days in  twelve calendar months. This Court further held, that control was retained by  BHEL; that respondents 1 to 14 had to work under the supervision of BHEL  and, in the circumstances, this Court refused to interfere with the award of  the Labour Court.

We need not go into the chequered litigation regarding execution of  the award which took place after the judgment of this Court. Suffice it to  state that, after the judgment of this Court dated 21.7.2003, the Assistant  Labour Commissioner ("ALC") passed an order on 1.12.2003 directing  BHEL to re-engage respondents 1 to 14 through the contractors in  compliance with award dated 5.7.1996.

Aggrieved by the order of the ALC, respondents 1 to 14 herein moved  the Uttranchal High Court vide Writ Petition No. 1279/03 stating that the  order of ALC be quashed and that BHEL should be directed to give  employment to respondents 1 to 14 herein and not through intermediary,  namely, the contractor.

By the impugned judgment dated 27.9.2004, after stating the above  facts, the High Court set aside the order of the ALC dated 1.12.2003 and  directed BHEL to reinstate respondents 1 to 14 herein in service directly.  Hence, this civil appeal. Shri Sudhir Chandra, learned senior counsel appearing for BHEL,  contended that the doctrine of merger has limited application to the facts of  the present case. He submitted that, when the Division Bench of this Court  upheld the award vide its judgment dated 21.7.2003, this Court had  confirmed the operative part of the award of the Labour Court which  directed BHEL to re-employ respondents 1 to 14 in their service or get the  said workers employed through an intermediary, namely, the contractor. He  submitted that the doctrine of merger applies to the operative part of the

3

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5  

award and not to the reasoning or observations in the award. In this  connection, learned senior counsel submitted that, an individual dispute was  raised by the workers under Section 2-A of the said 1947 Act complaining  about termination of services w.e.f. 1.12.1988. Learned senior counsel  further pointed out that, before the Labour Court it was the case of the  workers themselves that they were engaged by the contractor but the work  which they had performed was for BHEL. In this connection, reliance was  placed on the observations made by the Labour Court in its award (see page  76 of the SLP paper book). He submitted that, in the above circumstances,  the Labour Court had treated BHEL as the principal employer and the  contractor as an immediate employer. He submitted that, operative part of  the order has become final by reason of the judgment of this Court dated  21.7.2003. He urged, that the award was given on the basis of an individual  dispute under Section 2-A of the said 1947 Act; that the terms of the  reference indicate that the only question which the Labour Court was  required to decide was whether termination of services was justified and  lawful and, if not, the benefits/ relief which each of the workers were  entitled to. Learned senior counsel submitted that the workers in the present  case cannot claim direct employment from BHEL. He urged that the Labour  Court while granting reinstatement made an enabling provision by which the  said workers (respondents 1 to 14) were directed to be re-employed by  BHEL in the service directly or get them employed under their contractor. It  is not in dispute that BHEL has got said workers employed through that  contractor. The said workers continue to be the employees of the contractor  even today. Even today, they are getting the work and salary from the  contractor.

Learned senior counsel for the appellant further submitted that, the  subject of the dispute before the Labour Court was the validity of the  termination and not direct employment from BHEL. He submitted that, if the  said workers were to ask for direct employment from BHEL, they were  required to raise a regular industrial dispute not under Section 2-A but under  Section 2(l) of the said 1947 Act. He submitted that the cause of the said  workmen herein was not espoused by any union. If the workmen wanted  direct employment from BHEL or regularization, they were required to raise  a substantial industrial dispute before the tribunal; they were required to join  the regular union of BHEL as party respondent and in such an event the  matter was required to be adjudicated upon not by the Labour Court but by  the tribunal. He further pointed out,  that there is a regular union in the  industry; that the company was maintaining a waiting list of workers of  BHEL, who were required to be made permanent; that respondents 1 to 14  were never recruited directly by BHEL; that they had never applied for  employment against vacancies in BHEL, and if they had sought direct  employment with BHEL, then they were required to raise an industrial  dispute seeking abolition of contract labour after making the regular union a  party respondent. He, therefore, submitted that an individual dispute, though  need to be an industrial dispute under Section 2-A, cannot be converted into  an industrial dispute under Section 2(l) without a proper reference.

Shri V.C. Mishra, learned senior counsel appearing on behalf of some  of the respondents, submitted that in the earlier round of litigation, the  Labour Court, the High Court and the apex Court had held that respondents  1 to 14 were the employees of BHEL. He urged that, vide para 13 of the  decision of the apex Court, the findings recorded by the Labour Court and  the High Court were confirmed and that respondents 1 to 14 were directed to  be treated as employees of BHEL. In the circumstances, learned senior  counsel urged that the doctrine of merger was squarely applicable and,  therefore, the ALC had erred in directing BHEL to re-employ respondents    1 to 14 through the contractor. Learned senior counsel urged that, in the  circumstances, there was no reason to interfere with the impugned judgment  of the High Court directing BHEL to re-employ respondents 1 to 14 directly  as their workers.

Ms. Asha Jain Madan, learned counsel appearing for some of the  respondents, contended that in the earlier round of litigation respondents 1 to

4

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5  

14 had succeeded in all the courts. She heavily relied upon the observations  made in the judgment of the High Court confirmed by this Court stating that,  BHEL had resorted to a camouflage in order to avoid the provisions of the  said 1947 Act. She contended, that respondents 1 to 14 were malis, they  were required to look after the lawns of the company; that in the earlier  round, even after the award the company had refused to pay compensation to  the workers either directly or through the contractor; that the contractor had  disowned their liability; and, in the circumstances, the workers had to file an  application for implementation of the award. She contended that the  workmen who get out of job unless and, in the circumstances, it was  submitted that this Court should not interfere with the impugned judgment.  She further contended that engagement of workers through a camouflage,  keeping control over their work, termination of services unlawfully and  refusal to produce relevant records before the Labour Court are  circumstances which show that BHEL was the employer and respondents 1  to 14 were entitled to be directly employed with the company. Learned  counsel further contended that, the very basis of the award in the present  case was unlawful termination of services by BHEL through its contractor.  She submitted that the judgments of the High Court and this Court  upholding the award show that BHEL was the real employer and a  camouflage was created by BHEL to show that respondents 1 to 14 were the  employees of the contractor and not of the BHEL. In the circumstances,  learned counsel contended that respondents 1 to 14 should be employed by  BHEL as their employees. In this connection, learned counsel relied upon  the order passed by this Court in the case of Hotel Corporation of India &  anr.  v.  Balwant Rai Saluja & Ors. .  Learned counsel also relied upon the  judgment of this Court, referred above, in the case of  Bharat Heavey  Electricals Ltd.   v.   State of U.P. and Ors.   as also the judgment of this  Court in the case of  Steel Authority of India Ltd. and Ors.  v.  National  Union  Waterfront Workers and Ors. .

As stated above, the central question which we have to answer  concerns the subject of the dispute decided by the Labour Court vide award  dated 5.7.1996. The right to employment on setting aside of the earlier order  of termination, the right to wages and the right to obtain work from BHEL is  different from the right to status as employees of BHEL. Under the said  award respondents 1 to 14 were entitled to obtain work from BHEL through  its contractor. They were entitled to wages under the said award. However,  under the said award of the Labour Court there is no abolition of contract  labour. The Labour Court has not conferred the status of a workman qua  BHEL.  The Labour Court has not granted permanency to them. Per contra,  after holding that the work of mali was supervised and controlled by BHEL,  the award makes an enabling provision by directing BHEL to re-employ the  said workmen in their service or employ them through the contractor. In  fact, the operative part of the award further states that it is the contractors  who had failed to retain the workmen and terminated their services in breach  of Section 6-N of the said 1947 Act. This enabling direction is given on the  footing that the work carried out by these workmen was under control and  supervision of BHEL. The observations made in the judgment of the High  Court as well as in the judgment of this Court in Bharat Heavy Electricals  Ltd.2  (supra) have to be read in the context of the operative part of the  award. It is true that, observations have been made by this Court in the  above judgment in agreement with the views expressed by the High Court  that BHEL had resorted to a camouflage to get the work done through  contractor. However, since the work was obtained under supervision and  control of BHEL, the award directed these workmen to be employed directly  or through the contractor. Therefore, the observations of the High Court and  this Court have to be read in the light of the operative part of the award.  

For the above reasons, the judgments cited on behalf of respondents 1  to 14 have no application to the facts of the present case.  In those  judgments, a substantial industrial dispute was raised which is not the case  herein.  Therefore, they have no application to the present case.

There is one more reason for coming to the above conclusion. There is

5

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5  

a difference between an individual dispute which is deemed to be an  industrial dispute under Section 2-A of the said 1947 Act on one hand and  an industrial dispute espoused by the union in terms of Section 2(l) of the  said 1947 Act. An individual dispute which is deemed to be an industrial  dispute under Section 2-A concerns discharge, dismissal, retrenchment or  termination whereas an industrial dispute under Section 2(l) covers a wider  field. It includes even the question of status. This aspect is very relevant for  the purposes of deciding this case. In the case of  Radhey Shyam and anr.   v.  State of Haryana and anr.   it has been held after considering various  judgments of the Supreme Court that, Section 2-A contemplates nothing  more than to declare an individual dispute to be an industrial dispute. It does  not amend the definition of industrial dispute set out in Section 2(k) of the  Industrial Disputes Act, 1947 (which is similar to Section 2(l) of the said  1947 Act). Section 2-A does not cover every type of dispute between an  individual workman and his employer. Section 2-A enables the individual  worker to raise an industrial dispute, notwithstanding, that no other  workmen or union is a party to the dispute. Section 2-A applies only to  disputes relating to discharge, dismissal, retrenchment or termination of  service of an individual workman. It does not cover other kinds of disputes  such as bonus, wages, leave facilities etc.

As stated above, in the present case the award of the Labour Court has  also held that respondents 1 to 14 have proceeded their case on the footing  that they were engaged by the contractors, but the work they performed was  for BHEL. That is why the  operative part of the award says that the said  respondents shall be given work by BHEL as direct workmen or through its  contractor. The question which we have to answer is:  why did the Labour  Court provide for an enabling direction in its award? The answer is simple.  The Labour Court has not granted a status of direct employment per se  because BHEL has its own recognized union and that union was not made a  party respondent. Respondents 1 to 14 herein were not recruited directly in  BHEL; they had never applied for job in BHEL; the appointment letters  appear to have been given by the contractor; BHEL has its own waiting list  of workmen, who claimed permanency/ regularization; and they were not  before the Labour Court. In the circumstances, the Labour Court has enabled  BHEL either to directly employ respondents 1 to 14 or employ them through  the contractor. The contractor before us states that respondents 1 to 14 are  being given work by him, they were paid wages by the contractor. In the  circumstances, the ALC was right in directing BHEL to re-employ  respondents 1 to 14 either directly or through the contractor. This order was  passed by the ALC on 1.12.2003. The ALC was an execution court. The said  order is in terms of the award given by the Labour Court on 5.7.1996.

Accordingly, we set aside the impugned judgment of the High Court  by directing BHEL to re-employ respondents 1 to 14 directly or through its  contractor. This order will, however, not preclude the workmen from raising  an industrial dispute claiming status of direct workmen of the company after  joining the recognized union/ concerned union in the said Reference. This  order will not prevent the respondents herein from seeking abolition of  contract labour in accordance with law.

Accordingly, the civil appeal is disposed of. No order as to costs.